November 2, 2026

M10 Concrete Mix Design as per IS 10262:2019

The calculation follows the IS 10262:2019 procedure for target strength, water content, admixture reduction, entrapped air and aggregate proportioning. The numerical values are an initial trial mix and must be verified using actual laboratory materials and trial batches.

Introduction

M10 concrete has a characteristic compressive strength of 10 N/mm² at 28 days.

This article presents an illustrative M10 design mix using:

  • OPC 53 cement
  • 20 mm and 12.5 mm coarse aggregate
  • Zone II manufactured sand
  • Auramix 400 superplasticizer
  • Approximately 100 mm slump
  • Water-cement ratio of 0.60
  • Cement content of 250 kg/m³

This is a design-mix example and not a universal construction recipe. The final mix must be confirmed through laboratory trials, workability checks, cube testing and project approval.

1. Design stipulations

ItemAdopted value
Grade of concreteM10
Characteristic compressive strength10 N/mm² at 28 days
Type of mixDesign mix
CementOPC 53 grade conforming to IS 269
Maximum nominal size of aggregate20 mm
Coarse aggregate combination20 mm and 12.5 mm
Fine aggregateManufactured sand, Zone II
Exposure conditionMild exposure for the illustrative plain-concrete example
Target slump100 ± 25 mm
Method of placingPumping trial
Degree of supervisionGood
Chemical admixtureAuramix 400 superplasticizer
Adopted water-cement ratio0.60
Adopted cement content250 kg/m³
Entrapped air1%
Basis of calculationSaturated surface-dry aggregate condition

Important limitation

M10 should not be used automatically for structural RCC. The required minimum grade must be checked according to the exposure condition, structural drawings and project specification.

2. Suitable applications

M10 concrete may be used for approved applications such as:

  • Plain concrete
  • Lean concrete
  • Blinding concrete
  • Levelling courses
  • Foundation bedding
  • Non-structural base layers
  • Simple or temporary works

M10 should not be used automatically for:

  • Structural slabs
  • Structural beams
  • Structural columns
  • Load-bearing RCC members
  • Water-retaining structures
  • Aggressive or coastal exposure conditions

3. Material properties

MaterialAdopted value
OPC 53 cement specific gravity3.15
Fine aggregate specific gravity2.60
20 mm aggregate specific gravity2.63
12.5 mm aggregate specific gravity2.62
Water specific gravity1.00
Auramix 400 specific gravity1.09
Fine aggregate gradingZone II
Coarse aggregate combination50% 20 mm and 50% 12.5 mm by mass
Aggregate moistureTo be tested before batching
Aggregate absorptionTo be tested before batching

No GGBS or fly ash is included in this example. If a mineral admixture is added, the complete mix must be recalculated using the water-to-cementitious-materials ratio.

4. Target mean strength

For M10 concrete:

Characteristic strength, fck = 10 N/mm²

Since sufficient site test data is not assumed:

Standard deviation, S = 3.5 N/mm²

For M10 concrete:

Grade factor, X = 5.0 N/mm²

Target strength using standard deviation

Target mean strength:

f′ck = fck + 1.65S

f′ck = 10 + 1.65 × 3.5

f′ck = 15.78 N/mm²

Target strength using grade factor

f′ck = fck + X

f′ck = 10 + 5

f′ck = 15.00 N/mm²

The higher value is adopted:

Target mean strength = 15.78 N/mm²

The actual standard deviation should be recalculated when sufficient production test results are available.

5. Selection of water-cement ratio

For this illustrative plain-concrete example, adopt:

Water-cement ratio = 0.60

Since no mineral admixture is used:

Water-cementitious-materials ratio = 0.60

This value must be checked against the applicable exposure condition and project requirements.

6. Water content calculation

For 20 mm angular aggregate and 50 mm slump, the basic water content is:

Water content = 186 litres/m³

Target slump:

100 mm

Increase in slump:

100 − 50 = 50 mm

Number of 25 mm increments:

50 ÷ 25 = 2

Increase in water content:

2 × 3% = 6%

Water content before superplasticizer:

186 × 1.06 = 197.16 litres/m³

Assume a preliminary 24% water reduction through Auramix 400 based on trial performance:

197.16 × 0.76 = 149.84 litres/m³

Adopt:

Total design mixing water = 150 litres/m³

The actual water reduction must be confirmed through laboratory trials.

7. Cement content calculation

Cement content:

Cement = Water ÷ Water-cement ratio

Cement = 150 ÷ 0.60

Cement = 250 kg/m³

Adopt:

Cement content = 250 kg/m³

This value is greater than the illustrative minimum cement content of 220 kg/m³ for mild-exposure plain concrete.

8. Superplasticizer calculation

Adopt an initial Auramix 400 dosage of:

1.0% by mass of cement

Admixture quantity:

250 × 1.0 ÷ 100 = 2.50 kg/m³

Approximate admixture volume:

2.50 ÷ (1.09 × 1000) = 0.00229 m³

Therefore:

Auramix 400 = 2.50 kg/m³

The final dosage must be adjusted according to slump, slump retention, setting time, bleeding and segregation.

9. Entrapped air

For normal non-air-entrained concrete with 20 mm aggregate:

Entrapped air = 1%

Entrapped air volume = 0.01 m³

10. Aggregate volume calculation

Volume of cement

Vc = 250 ÷ (3.15 × 1000)

Vc = 0.07937 m³

Volume of water

Vw = 150 ÷ (1.00 × 1000)

Vw = 0.15000 m³

Volume of admixture

Vadmixture = 0.00229 m³

Volume of entrapped air

Vair = 0.01000 m³

Volume of total aggregate

Vaggregate = 1 − (Vc + Vw + Vadmixture + Vair)

Vaggregate = 1 − (0.07937 + 0.15000 + 0.00229 + 0.01000)

Vaggregate = 0.75834 m³

Therefore:

Total aggregate volume = 0.75834 m³

11. Coarse and fine aggregate proportion

For 20 mm aggregate and Zone II fine aggregate:

  • Coarse aggregate volume at w/c 0.50 = 0.62
  • Adopted w/c = 0.60
  • Reduction for w/c adjustment = 0.02

Corrected coarse aggregate fraction:

0.62 − 0.02 = 0.60

For the preliminary pumping trial, reduce the coarse aggregate fraction by 10%:

0.60 × 0.90 = 0.54

Adopted coarse aggregate fraction:

0.54

Fine aggregate fraction:

1 − 0.54 = 0.46

Therefore:

  • Coarse aggregate fraction = 0.54
  • Fine aggregate fraction = 0.46

The pumping adjustment is a trial assumption and must be verified using actual concrete flow and pump performance.

12. Coarse aggregate calculation

Volume of coarse aggregate

VCA = 0.75834 × 0.54

VCA = 0.40950 m³

Assume the coarse aggregate is divided equally by mass:

  • 20 mm aggregate = 50%
  • 12.5 mm aggregate = 50%

Using the specific gravities of both fractions:

M20/(2.63 × 1000) + M12.5/(2.62 × 1000) = 0.40950

Calculated quantities:

  • 20 mm aggregate = 537.5 kg/m³
  • 12.5 mm aggregate = 537.5 kg/m³

Adopt:

  • 20 mm aggregate = 538 kg/m³
  • 12.5 mm aggregate = 538 kg/m³

The 50:50 combination must be confirmed through combined grading and trial batching.

13. Fine aggregate calculation

Volume of fine aggregate

VFA = 0.75834 × 0.46

VFA = 0.34884 m³

Mass of fine aggregate

Fine aggregate = 0.34884 × 2.60 × 1000

Fine aggregate = 906.98 kg/m³

Adopt:

Fine aggregate = 907 kg/m³

14. Absolute-volume check

MaterialQuantitySpecific gravityVolume
Cement250 kg3.150.07937 m³
Water150 kg1.000.15000 m³
Auramix 4002.50 kg1.090.00229 m³
Fine aggregate907 kg2.600.34884 m³
20 mm aggregate537.5 kg2.630.20436 m³
12.5 mm aggregate537.5 kg2.620.20514 m³
Entrapped air——0.01000 m³
Total——Approximately 1.000 m³

15. Final M10 trial mix

Quantities per cubic metre

MaterialQuantity
OPC 53 cement250 kg
Total design mixing water150 litres
Auramix 4002.50 kg
Manufactured sand, Zone II907 kg
20 mm coarse aggregate538 kg
12.5 mm coarse aggregate538 kg
Entrapped air1%
Water-cement ratio0.60
Target slump100 ± 25 mm
Approximate fresh concrete mass2,385 kg/m³

Approximate mass ratio

Cement:Fine aggregate:20 mm aggregate:12.5 mm aggregate

1 : 3.63 : 2.15 : 2.15

Combined aggregate ratio:

Cement:Fine aggregate:Coarse aggregate

1 : 3.63 : 4.30

This is a calculated design-mix ratio and must not be confused with the nominal 1:3:6 ratio.

16. Moisture correction

The above quantities are based on saturated surface-dry aggregates.

Free water from wet aggregate

Free water = (Moisture − Absorption) ÷ 100 × Dry aggregate mass

When moisture is greater than absorption, deduct the free water from the mixing water.

Water absorbed by dry aggregate

Water deficit = (Absorption − Moisture) ÷ 100 × Dry aggregate mass

When absorption is greater than moisture, provide additional water or pre-wet the aggregate.

Corrected water to be added

Water to add = Design water − Free surface water + Absorption deficit

The water present in the liquid admixture must also be considered if required by the product data sheet.

17. Trial-batch procedure

  1. Use the same cement, aggregates and admixture intended for the project.
  2. Confirm aggregate grading, moisture and absorption.
  3. Weigh all ingredients accurately.
  4. Add part of the mixing water to the mixer.
  5. Add coarse aggregate, fine aggregate and cement.
  6. Add the remaining corrected water.
  7. Add Auramix 400 according to the approved trial procedure.
  8. Mix until a uniform concrete is obtained.
  9. Measure the slump immediately after mixing.
  10. Check bleeding, segregation and cohesiveness.
  11. Check slump retention after the required transport time.
  12. Cast concrete cubes as required by the project quality plan.
  13. Cure the specimens properly.
  14. Test compressive strength at the specified ages.
  15. Check fresh concrete density and actual yield.
  16. Finalize the mix only after reviewing all test results.

Do not add uncontrolled water at the site.

18. Quality-control requirements

The trial mix should satisfy:

  • Target slump at the required time
  • No unacceptable bleeding
  • No segregation
  • Required 28-day compressive strength
  • Required density and yield
  • Required durability
  • Pumpability, where applicable
  • Cement-admixture compatibility
  • Project-specific temperature and placing requirements

19. Important technical notes

  • M10 is not a normal structural RCC grade.
  • The mix is an initial design-mix trial and not a guaranteed universal recipe.
  • The 24% water reduction is a preliminary assumption.
  • Auramix 400 dosage must be confirmed by trial.
  • GGBS or fly ash is not included in this calculation.
  • If mineral admixture is added, recalculate the water-to-cementitious-materials ratio.
  • Aggregate moisture correction is compulsory before batching.
  • If bucket placement is used instead of pumping, conduct a separate trial.
  • The final mix must be approved by the responsible engineer.

Frequently asked questions

What is the M10 concrete mix ratio?

A design mix does not have one universal fixed ratio. In this example, the approximate mass ratio is:

1 : 3.63 : 4.30

for cement:fine aggregate:combined coarse aggregate.

The nominal 1:3:6 ratio is a separate volume-batching approach.

What is the cement content of this M10 mix?

The adopted cement content is:

250 kg/m³

This is calculated from 150 litres of water and a water-cement ratio of 0.60.

Why is superplasticizer used?

Superplasticizer helps obtain the required slump with lower water demand. It does not automatically guarantee strength or permit uncontrolled cement reduction.

Can the water be reduced further?

Yes, but only after laboratory trials confirm the required slump, strength, setting behaviour and durability.

Can GGBS be added?

Yes, if approved. However, the cementitious content, w/cm ratio, curing period and aggregate calculations must be revised.

Can this mix be pumped?

It includes a preliminary pumpability adjustment, but actual pumpability must be confirmed by a pump trial.

Related resources

About T Square Civil Engineering

T Square Civil Engineering is a free civil engineering learning platform providing concrete mix-design guidance, construction calculators, RCC design information, quantity-estimation tools, laboratory-test procedures and practical construction knowledge.

Disclaimer

The information on this website is provided for educational purposes only.

It does not replace project-specific engineering design, professional advice, approved drawings or construction specifications. Examples, calculations and suggested procedures should not be adopted directly for construction without appropriate verification. Always check the latest applicable standards and amendments, local requirements, project specifications, material-test results and site conditions. Final design, testing, acceptance and construction decisions should be made by qualified professionals and the responsible project authorities.

Standards referenced

  • IS 10262:2019 — Concrete Mix Proportioning — Guidelines
  • IS 456:2000 — Plain and Reinforced Concrete — Code of Practice
  • IS 383 — Coarse and Fine Aggregate for Concrete
  • IS 269 — Ordinary Portland Cement
  • IS 9103 — Concrete Admixtures
  • IS 1199 — Methods of Sampling and Analysis of Concrete
  • IS 516 — Compressive Strength Testing of Concrete

Leave a Reply