Concrete mix design is normally calculated for 1 m³ of concrete, but the actual volume produced from a batch may differ slightly from the theoretical design volume.
This difference can be checked by measuring the density of fresh concrete and calculating the actual concrete yield.
Fresh-concrete density is therefore useful not only as a laboratory test but also as a practical quality-control check for:
- concrete mix design;
- trial batches;
- batching accuracy;
- air content;
- aggregate moisture;
- concrete yield; and
- production consistency.
In Indian practice, the density of fresh concrete is determined using IS 1199 (Part 3):2018 – Fresh Concrete — Methods of Sampling, Testing and Analysis: Part 3 Determination of Density of Fresh Concrete.
This article explains:
- fresh-concrete density;
- the difference between calculated and measured density;
- the density test;
- concrete yield calculation;
- relative yield;
- under-yield and over-yield;
- batch-size correction;
- effect of entrapped air and moisture;
- common mistakes; and
- practical worked examples.
For the complete mix-design sequence, start with our Concrete Mix Design Hub and Concrete Mix Design Procedure as per IS 10262:2019.
Page Contents
What Is Fresh Concrete Density?
Fresh concrete density is the mass of freshly mixed concrete contained in a known volume.
It is expressed as:
kg/m³
The basic relationship is:
Fresh Concrete Density = Mass of Fresh Concrete ÷ Volume Occupied
Fresh concrete density is sometimes informally called:
unit weight of fresh concrete
However, in SI concrete testing, density in kg/m³ is the clearer term.
Why Fresh Concrete Density Matters
Fresh-concrete density can help identify whether the actual concrete being produced is reasonably consistent with the calculated mix.
Unexpected density changes may indicate variation in:
- aggregate specific gravity;
- aggregate moisture;
- batching quantities;
- entrapped or entrained air;
- water addition;
- admixture dosage;
- segregation; or
- material proportions.
Density should therefore be considered together with:
- slump or other workability measurement;
- air content where applicable;
- temperature;
- concrete appearance;
- batching records; and
- strength results.
Density alone cannot identify the exact cause of a concrete problem.
Calculated Mass of 1 m³ of Concrete
After a concrete mix has been proportioned, the design quantities are usually expressed in:
kg/m³
Suppose a mix contains:
| Material | Design Quantity |
|---|---|
| Cement | 360 kg/m³ |
| GGBS | 60 kg/m³ |
| Water | 165 kg/m³ |
| Fine aggregate | 720 kg/m³ |
| Coarse aggregate | 1,100 kg/m³ |
| Chemical admixture | 4 kg/m³ |
Total design mass:
360 + 60 + 165 + 720 + 1,100 + 4
= 2,409 kg/m³
Therefore, the calculated mass of the designed one cubic metre is:
2,409 kg
If the absolute-volume calculation balances exactly to 1 m³, this corresponds to a calculated fresh-concrete mass per design cubic metre of approximately:
2,409 kg/m³
The actual measured fresh density may be slightly different.
Calculated Density vs Measured Fresh Density
These should not be confused.
Calculated Fresh Mass per Design Volume
This is obtained from the mix-design quantities.
For a mix designed for 1 m³:
Calculated mass per m³ = Sum of design material masses
Measured Fresh Density
This is determined by weighing a known volume of actual freshly mixed concrete.
The measured value reflects the real batch, including the effects of:
- actual material densities;
- actual air content;
- batching variation;
- moisture;
- compaction of the test sample; and
- production conditions.
Comparing the two can provide useful information about concrete yield and consistency.

Standard for Fresh Concrete Density
The density of fresh concrete is determined in Indian practice in accordance with:
IS 1199 (Part 3):2018
The test uses a container or measure having a known calibrated volume.
A representative sample of fresh concrete is placed in the measure, compacted according to the applicable test procedure, struck off level and weighed.
The mass of concrete inside the known measure is then used to calculate density.
Basic Density Test Formula
Let:
M1 = mass of empty measure
M2 = mass of measure filled with fresh concrete
V = calibrated volume of measure
Then:
Mass of fresh concrete = M2 − M1
and:
Fresh Concrete Density = (M2 − M1) ÷ V
Where:
- mass is in kg;
- volume is in m³; and
- density is obtained in kg/m³.
Worked Example – Fresh Concrete Density
Suppose:
Mass of empty calibrated measure:
8.33 kg
Mass of measure + fully compacted fresh concrete:
41.12 kg
Calibrated volume of measure:
0.01374 m³
Step 1: Calculate Concrete Mass
41.12 − 8.33
= 32.79 kg
Step 2: Calculate Fresh Density
32.79 ÷ 0.01374
≈ 2,386 kg/m³
Therefore, the calculated fresh-concrete density is approximately:
2,386 kg/m³
As per IS 1199 (Part 3):2018, the density test result should be reported to the nearest 10 kg/m³.
Therefore, the reported density is:
2,390 kg/m³
The actual calibrated volume of the measure should always be used rather than relying only on its nominal dimensions.
What Is Concrete Yield?
Concrete yield is the actual volume of fresh concrete produced from a batch.
The mix may be proportioned for:
1.000 m³
but the real batch may produce slightly:
- more than 1 m³; or
- less than 1 m³.
This actual volume is called the yield.
Concrete Yield Formula
If the total mass of all materials actually entering the batch is known and the fresh-concrete density has been measured:
Actual Yield = Total Batch Mass ÷ Measured Fresh Concrete Density
Where:
- total batch mass is in kg;
- density is in kg/m³; and
- yield is in m³.
What Should Be Included in Total Batch Mass?
For a yield calculation, the batch mass should represent the actual mass of concrete ingredients entering the mixer.
Depending on the batching system, this may include:
- cement;
- supplementary cementitious materials;
- fine aggregate;
- coarse aggregate;
- actual water entering the batch;
- water contained in wet aggregates where represented in wet aggregate mass;
- liquid admixture; and
- other specified constituents.
Avoid double-counting aggregate moisture.
For example, if the wet aggregate mass already includes moisture, do not separately add the same contained water again to the total mass.
The batching record should be used consistently.
Worked Example – Actual Yield
Using the previous mix:
Total actual batch mass:
2,409 kg
Measured fresh density:
2,386 kg/m³
Then:
Yield = 2,409 ÷ 2,386
= 1.010 m³ approximately
Therefore, a batch intended to represent approximately 1 m³ has actually yielded about:
1.010 m³
What Is Relative Yield?
Relative yield compares actual produced volume with the intended batch volume.
The formula is:
Relative Yield = Actual Yield ÷ Intended Yield
If expressed as a percentage:
Relative Yield (%) = Actual Yield ÷ Intended Yield × 100
For the example:
Actual yield:
1.010 m³
Intended yield:
1.000 m³
Therefore:
Relative Yield = 1.010 ÷ 1.000
= 1.010
or:
101.0%
This represents approximately:
1.0% over-yield
Relative yield is used here as an additional production/QC calculation; it is not the density test result specified by IS 1199 (Part 3):2018.
What Is Under-Yield?
Under-yield means the batch produces less concrete volume than intended.
Suppose:
Total batch mass = 2,409 kg
Measured fresh density = 2,445 kg/m³
Then:
Yield = 2,409 ÷ 2,445
= 0.985 m³ approximately
Relative yield:
0.985 ÷ 1.000 × 100
= 98.5% approximately
Therefore:
Under-yield ≈ 1.5%
The batch has produced slightly less than the intended 1 m³.
What Is Over-Yield?
Over-yield means the calculated actual volume is greater than the intended batch volume.
For example:
Actual yield:
1.010 m³
Intended yield:
1.000 m³
Therefore:
Over-yield ≈ 1.0%
Over-yield should not automatically be considered beneficial.
Unexpected over-yield may indicate:
- higher air content;
- lower-than-expected fresh density;
- excess water;
- incorrect aggregate moisture correction;
- material density variation;
- weighing error; or
- other batching differences.
The cause should be investigated if the deviation is significant or inconsistent.
Why Density and Yield Are Inversely Related
For the same total batch mass:
Yield = Batch Mass ÷ Density
Therefore:
If measured density decreases:
calculated yield increases
If measured density increases:
calculated yield decreases
This does not mean density should be deliberately lowered to obtain more concrete.
Lower density may result from:
- increased air;
- material changes;
- excessive water; or
- other undesirable changes.
Concrete quality requirements still govern.
Effect of Entrapped Air on Fresh Density
Air occupies volume but contributes negligible mass.
Therefore, if the air content increases while the constituent masses remain similar, the fresh density generally decreases.
This can produce an apparent increase in calculated yield.
For this reason, unexpected density or yield changes should be reviewed together with air-content information where applicable.
For the detailed concept, see our Entrapped Air in Concrete Mix Design.
Entrapped Air vs Poor Compaction of the Density Sample
The fresh-density test sample must be prepared and compacted correctly according to the applicable method.
If the test measure contains excessive unintended voids because the test sample was poorly consolidated, the measured density may be artificially low.
This would make the calculated yield appear artificially high.
Therefore:
incorrect density-test preparation can produce an incorrect yield calculation.
The test procedure must be followed consistently.
Effect of Aggregate Specific Gravity
Aggregate forms a large portion of concrete mass.
Therefore, changes in aggregate specific gravity can affect fresh-concrete density.
For example, two aggregates occupying the same absolute volume may have different masses if their specific gravities differ.
Concrete produced using the heavier aggregate may therefore have a higher fresh density even when the concrete volume is similar.
This is why fresh density should not be compared between different concrete mixes without considering the actual materials.
Effect of Aggregate Moisture
Aggregate moisture affects:
- wet aggregate batch mass;
- separately added water;
- actual free water;
- workability; and
- potentially concrete density and yield.
Suppose the fine aggregate contains more surface moisture than assumed.
If the batch is not corrected properly:
- excess water may enter the concrete;
- wet sand mass may differ from design assumptions;
- slump may increase;
- density may change; and
- actual yield may differ.
For the complete procedure, see our Moisture Correction in Concrete Mix Design.
Avoid Double-Counting Aggregate Moisture
This is important when calculating actual batch mass.
Suppose the design requires:
700 kg SSD fine aggregate
but the actual wet batch mass is:
728 kg
because the stockpile contains moisture.
If 728 kg is used as the actual fine-aggregate batch mass, the moisture contained in that quantity is already part of the total batch mass.
Do not also add that same contained water as another separate mass when calculating total concrete batch mass.
Only the water actually entering the concrete should be counted once.
Density and the Absolute Volume Method
The absolute-volume method calculates the theoretical material volumes used to form one cubic metre of concrete.
The basic relationship is:
Absolute Volume = Mass ÷ (Specific Gravity × 1000)
When the absolute volumes of:
- cement;
- SCMs;
- water;
- admixture;
- fine aggregate;
- coarse aggregate; and
- air
are combined, they should approximately equal the intended concrete volume.
Fresh-density measurement provides an independent practical check on what the actual batch has produced.
For the full theoretical calculation, see our Absolute Volume Method for Concrete Mix Design.
Density and Trial Mix Verification
A trial mix should not be approved based only on calculated quantities.
Fresh concrete may also be checked for:
- slump;
- cohesiveness;
- segregation;
- bleeding;
- temperature;
- fresh density;
- air content where required;
- finishing characteristics;
- pumpability where applicable; and
- compressive strength.
Fresh density can help identify whether a trial behaves consistently with the intended volume balance.
See our Concrete Trial Mix Procedure.
Trial Batch Quantity
A laboratory trial does not normally require a full 1 m³ batch.
Suppose the design quantities are:
| Material | Quantity per m³ |
|---|---|
| Cement | 360 kg |
| GGBS | 60 kg |
| Water | 165 kg |
| Fine aggregate | 720 kg |
| Coarse aggregate | 1,100 kg |
| Admixture | 4 kg |
For a:
0.05 m³ trial batch
multiply each quantity by:
0.05
Therefore:
Cement:
360 × 0.05 = 18.0 kg
GGBS:
60 × 0.05 = 3.0 kg
Water:
165 × 0.05 = 8.25 kg
Fine aggregate:
720 × 0.05 = 36.0 kg
Coarse aggregate:
1,100 × 0.05 = 55.0 kg
Admixture:
4 × 0.05 = 0.20 kg
These are preliminary trial-batch quantities before applying any required actual aggregate moisture corrections.
Actual Yield of a Laboratory Trial Batch
Suppose the total actual mass of the trial batch is:
120.5 kg
and measured fresh density is:
2,410 kg/m³
Then:
Actual yield = 120.5 ÷ 2,410
= 0.0500 m³
The trial has produced approximately the intended:
0.05 m³
Example of Trial Batch Under-Yield
Suppose a trial was intended to produce:
0.050 m³
but the calculated actual yield is:
0.048 m³
Relative yield:
0.048 ÷ 0.050
= 0.96
or:
96%
Therefore:
Under-yield = 4%
Before changing the mix, investigate:
- density-test accuracy;
- batching masses;
- material losses;
- mixer retention;
- aggregate moisture;
- air content; and
- calculation inputs.
Do not immediately redesign the concrete because of one unexpected result.
Batch-Size Correction Without Changing Mix Proportions
Sometimes the proportions are satisfactory, but the laboratory batch simply needs to be scaled to produce a required test volume.
Suppose:
Required trial volume:
0.050 m³
Measured actual trial yield:
0.048 m³
If the objective is only to increase the batch quantity while keeping the same proportions:
Scale Factor = Required Volume ÷ Actual Yield
Therefore:
Scale Factor = 0.050 ÷ 0.048
= 1.0417
All constituent batch masses can then be multiplied by approximately:
1.0417
to produce the required trial quantity while preserving the same proportions.
This is a batch-size adjustment, not a change in the concrete mix proportions.
If the yield discrepancy is unexplained or significant, identify the cause before routinely applying a correction factor.
Do Not Correct Only One Ingredient
If the intention is only to increase the total batch volume while maintaining the same approved concrete proportions, all ingredients should be scaled consistently.
For example, do not correct under-yield by adding only:
- more coarse aggregate;
- more sand; or
- more water.
Changing only one constituent changes the mix itself.
Yield and Actual Cement Content per Cubic Metre
Yield also affects the actual constituent quantity represented per cubic metre of produced concrete.
Suppose a batch contains:
Cement = 360 kg
Actual yield = 1.010 m³
Actual cement represented per cubic metre is:
360 ÷ 1.010
≈ 356.4 kg/m³
If instead the batch yields:
0.985 m³
then:
360 ÷ 0.985
≈ 365.5 kg/m³
Therefore, a meaningful yield deviation changes the effective constituent quantity per actual cubic metre.
This is one reason concrete yield is important in production control.
Yield and Water-Cementitious Ratio
Yield does not directly change the mass ratio of water to cementitious material within a uniformly batched concrete batch.
For example, if the batch contains:
Water = 165 kg
Cementitious material = 420 kg
then:
w/cm = 165 ÷ 420
= 0.393
Changing the calculated yield does not by itself alter this batch mass ratio.
However, if the unexpected yield is caused by:
- excess water;
- incorrect moisture correction;
- batching error; or
- material loss,
then the actual w/cm may also have changed.
Therefore, the cause of the yield difference matters.
Yield and Chemical Admixture
Liquid admixture contributes both:
- mass; and
- volume.
Its mass should be included in the batch mass used for yield calculation.
Its specific gravity is also used in the theoretical absolute-volume calculation.
For detailed dosage calculation, see our Superplasticizer in Concrete Mix Design.
Density and Pumped Concrete
Pumping can influence the measured condition of concrete at the discharge point because pumping may change:
- air content;
- temperature;
- workability;
- segregation behaviour; and
- concrete consistency.
For important pumping operations, density may be measured at appropriate locations as part of the project quality-control programme.
Where before-and-after pumping measurements are compared, use representative samples and consistent test methods.
See our Pumped Concrete Mix Design.
Fresh Density Is Not Hardened Concrete Density
Do not confuse:
fresh concrete density
with:
hardened concrete density
Fresh density is measured while concrete is still plastic.
Hardened density is measured after concrete has hardened and is governed by a different test procedure.
Moisture loss, hydration, curing and internal pore structure can influence hardened-concrete density.
Therefore, the two values should not be treated as interchangeable.
Density Is Not Specific Gravity
Fresh-concrete density and material specific gravity are also different.
Fresh Concrete Density
Unit:
kg/m³
It represents mass per unit volume of the fresh concrete mixture.
Specific Gravity
Dimensionless.
It compares the density of a material with the density of water.
Specific gravity is used in the absolute-volume calculation, while fresh density is measured from the actual concrete.
Density Is Not Bulk Density of Aggregate
Aggregate bulk density includes the voids between loose aggregate particles.
Fresh-concrete density represents the mass of compacted fresh concrete per unit volume.
Do not use aggregate bulk density as a substitute for fresh-concrete density.
Reasons for Low Measured Fresh Density
A lower-than-expected fresh density may be associated with:
- higher air content;
- lower-density aggregates;
- excessive voids in the test sample;
- additional water;
- incorrect batching;
- segregation;
- incorrect moisture correction; or
- material changes.
Do not diagnose the problem from density alone.
Review the complete batch and test information.
Reasons for High Measured Fresh Density
A higher-than-expected density may be associated with:
- lower air content;
- denser aggregate;
- different material proportions;
- moisture variation;
- batching error; or
- incorrect test procedure.
Again, investigate the complete system.
Density Variation Between Concrete Grades
It is incorrect to assume that every:
- M20;
- M30;
- M40; or
- M50
concrete must have one fixed fresh density.
Density depends strongly on:
- aggregate density;
- aggregate proportion;
- cementitious content;
- water content;
- air content; and
- admixtures.
Two M30 mixes using different aggregates may have different fresh densities.
Concrete grade alone does not determine density.
Density Variation Between Aggregate Sources
Suppose Aggregate A has a specific gravity of:
2.75
and Aggregate B has a specific gravity of:
2.55
Concrete containing Aggregate A may have a higher fresh density if other factors are similar.
Therefore, historical density values from one quarry should not automatically be adopted after changing aggregate source.
Fresh Density and Concrete Production Control
Fresh density can be tracked over time as part of production quality control.
A stable concrete system should generally show reasonably consistent values when:
- materials;
- proportions;
- air content;
- moisture corrections; and
- batching procedures
remain similar.
A sudden density shift can act as a warning that something has changed.
The cause should then be investigated.
Suggested Trial-Mix Record
A practical record may include:
| Parameter | Trial Result |
|---|---|
| Mix reference | ______ |
| Date | ______ |
| Concrete grade | ______ |
| Intended batch volume | ______ m³ |
| Total actual batch mass | ______ kg |
| Empty measure mass | ______ kg |
| Filled measure mass | ______ kg |
| Measure volume | ______ m³ |
| Measured fresh density | ______ kg/m³ |
| Calculated yield | ______ m³ |
| Relative yield | ______ % |
| Slump | ______ mm |
| Concrete temperature | ______ °C |
| Air content, if tested | ______ % |
| Remarks | ______ |
This allows density and yield results to be compared with:
- workability;
- air content;
- batching data; and
- strength results.
Complete Worked Example
Consider the following 1 m³ design:
| Material | Quantity |
|---|---|
| Cement | 360 kg |
| GGBS | 60 kg |
| Water | 165 kg |
| Fine aggregate | 720 kg |
| Coarse aggregate | 1,100 kg |
| Admixture | 4 kg |
Step 1: Calculate Total Batch Mass
360 + 60 + 165 + 720 + 1,100 + 4
= 2,409 kg
Step 2: Measure Fresh Density
Suppose:
Empty measure = 7.85 kg
Filled measure = 31.71 kg
Measure volume = 0.010 m³
Concrete mass:
31.71 − 7.85 = 23.86 kg
Density:
23.86 ÷ 0.010
= 2,386 kg/m³
Step 3: Calculate Actual Yield
Yield = 2,409 ÷ 2,386
= 1.010 m³ approximately
Step 4: Calculate Relative Yield
1.010 ÷ 1.000 × 100
= 101.0%
Step 5: Calculate Yield Difference
The batch is approximately:
1.0% over the intended volume
This result should be reviewed together with:
- measured air content if available;
- moisture corrections;
- batching records;
- material properties; and
- previous density results.
Do not alter the approved mix merely because of one small isolated deviation.
Common Mistakes
Assuming Calculated Mass Equals Measured Density
The calculated sum of kg/m³ is a theoretical design quantity.
Measured density comes from the actual fresh concrete.
Using an Unknown Measure Volume
The density test requires a known or calibrated container volume.
Forgetting to Subtract the Empty Measure Mass
Use only the net mass of concrete.
Using Litres Directly Without Conversion
If volume is given in litres:
1 litre = 0.001 m³
For example:
10 litres = 0.010 m³
Confusing Density With Yield
Density:
kg/m³
Yield:
m³ produced from the batch
Ignoring Aggregate Moisture
Moisture can change both batching mass and effective water.
Double-Counting Moisture Water
Do not count the same aggregate moisture twice in the total batch mass.
Correcting Yield by Adding Water
Adding water changes concrete performance and potentially the w/cm ratio.
Yield correction should not be made by uncontrolled water addition.
Scaling Only One Ingredient
If only the batch quantity must be increased while preserving proportions, scale all ingredients consistently.
Redesigning the Mix From One Density Result
Verify test accuracy and repeatability before changing an approved mix.
Quick Formula Reference
| Calculation | Formula |
|---|---|
| Net concrete mass | Filled measure mass − Empty measure mass |
| Fresh density | Net concrete mass ÷ Measure volume |
| Actual yield | Total batch mass ÷ Measured fresh density |
| Relative yield | Actual yield ÷ Intended yield |
| Relative yield (%) | Actual yield ÷ Intended yield × 100 |
| Batch scale factor | Required volume ÷ Actual yield |
| Actual constituent per m³ | Constituent batch mass ÷ Actual yield |
Fresh Density and the Concrete Mix Design Calculator
Our Concrete Mix Design Calculator as per IS 10262:2019 calculates preliminary quantities required for the selected concrete volume.
These calculated quantities are the starting point.
The measured fresh density and actual yield provide useful production checks after the concrete is physically mixed.
The complete workflow is therefore:
Mix-design calculation
↓
Trial-batch quantities
↓
Moisture correction
↓
Concrete mixing
↓
Fresh-concrete tests
↓
Measured fresh density
↓
Actual yield calculation
↓
Workability and strength verification
↓
Final production approval
Frequently Asked Questions
What is the density of fresh concrete?
Fresh-concrete density is the mass of fresh concrete per unit volume, normally expressed in kg/m³.
Which IS code is used for fresh concrete density?
Fresh-concrete density is determined in accordance with IS 1199 (Part 3):2018.
What is the formula for fresh concrete density?
Density = Net mass of fresh concrete ÷ Volume of measure
What is concrete yield?
Concrete yield is the actual volume of fresh concrete produced from a batch.
How is concrete yield calculated?
Yield = Total batch mass ÷ Measured fresh-concrete density
What is relative yield?
Relative yield is the ratio of actual produced volume to intended volume.
What does under-yield mean?
Under-yield means the actual volume produced is less than the intended batch volume.
What does over-yield mean?
Over-yield means the calculated actual volume is greater than the intended batch volume.
Is over-yield always good?
No. Unexpected over-yield may be associated with higher air content, excess water, material variation or batching error.
Does air content affect fresh concrete density?
Yes. Higher air volume generally reduces fresh density when other factors are similar.
Does aggregate specific gravity affect concrete density?
Yes. Heavier or lighter aggregates can significantly influence fresh-concrete density.
Can yield be corrected by adding water?
No. Uncontrolled water addition can change the water-cementitious ratio and concrete performance.
How do I increase a trial batch volume without changing the mix ratio?
Calculate a scale factor:
Required volume ÷ Actual yield
and multiply all constituent quantities by the same factor, provided the concrete proportions themselves are satisfactory.
Related Concrete Mix Design Resources
Continue with these T Square Civil resources:
Concrete Mix Design Procedure as per IS 10262:2019
Concrete Mix Design Calculator as per IS 10262:2019
Absolute Volume Method for Concrete Mix Design
Entrapped Air in Concrete Mix Design
Moisture Correction in Concrete Mix Design
Superplasticizer in Concrete Mix Design
Nominal Maximum Aggregate Size in Concrete Mix Design
Conclusion
Fresh-concrete density connects the theoretical concrete mix design with the actual concrete produced in the mixer.
The density test determines:
mass of fresh concrete per known volume
using:
Fresh Density = Net Concrete Mass ÷ Measure Volume
Once the measured density is known, actual concrete yield can be calculated as:
Actual Yield = Total Batch Mass ÷ Measured Fresh Density
This allows the engineer to check whether an intended batch volume has produced:
- approximately the correct quantity;
- under-yield; or
- over-yield.
Unexpected yield differences should not be corrected blindly.
First investigate:
batching accuracy + aggregate moisture + air content + material density + water addition + test procedure + material losses
If the concrete proportions are satisfactory and only the laboratory batch quantity needs adjustment, all ingredients may be scaled by the same factor so that the mix proportions remain unchanged.
Fresh density and yield should therefore be used as part of a complete concrete quality-control system together with:
workability + air content where applicable + moisture correction + trial-mix behaviour + compressive strength + production records
Engineering note: Use the latest applicable Indian Standards, approved project specifications, calibrated test equipment and representative fresh-concrete samples when measuring density and evaluating concrete yield.
